CCWD trustees begin eminent domain process
“A public hearing has been scheduled before the Clark County Water Reclamation District Board of Trustees regarding the acquisition by eminent domain of a right-of-way on the former Mohave Generating Station property.
According to background documents before the trustees, Laughlin Lift Station 2 conveys more than 600,000 gallons of wastewater daily from the west side of Laughlin to the treatment facility via 11,320 linear feet of a pressurized force main and 3,060 linear feet of gravity sewer. The pipelines were installed in 1985 under a letter of license agreement, but a recent assessment of the pipelines, “found that over half of the existing force main and the entire existing gravity sewer was constructed outside of the defined license agreement.””
Fairman, Julie. The Laughlin Nevada Times 22 October 2013.